Rows of server racks in a data centre

Knowledge page · Data centre

Data centres: power, cooling and efficiency

A data centre is a building that must deliver power and cooling to the IT equipment without pause. Here is the power path all the way to the server, the requirements for availability and temperature – and the figures data centres over 500 kW must now report.

Class 1–4availability, EN 50600
18–27 °Crecommended inlet, ASHRAE
≥ 500 kWIT power = annual reporting

Updated · Norwerk

01

Power

How the power reaches the server, and how the path is made robust.

In short

The power path from grid to server

The power passes many links before it reaches the server: transformer, main switchboard, UPS, distribution board (PDU) and the outlets in the rack. The generator plant connects at the main switchboard, and the UPS with battery or flywheel bridges until it has taken over.

Every link can fail. That is why a data centre’s uptime depends as much on the distribution after the UPS as on the UPS itself.

Emergency power systems: the whole chain

MainsMedium voltageTransformer10/0.4 kVMain switchboard+ generator plantUPS+ battery or flywheelPDUDistribution in the roomRack PDUOutlets in the rackServerThe IT load

A/B supply

Two paths all the way to the rack

In a redundant data centre every rack gets two supplies, A and B, from separate UPS systems and switchboards. Most servers have two power supplies and can use both paths. Choose a situation and see what happens.

The redundancy only holds if each path can carry the whole load alone. If A and B are each loaded above 50 %, the remaining path trips when the other drops out.

Supply ASupply BServerPSU 1PSU 2STSSingle PSU

The server has two power supplies (PSUs), each connected to its own supply path. Each PSU can carry the whole server alone.

Borri STS 300

Class 1Class 2Class 3Class 4
Principle of the power supply. Dashed: path on standby.

EN 50600

Four availability classes

The European data centre standard EN 50600 divides power supply and distribution into four classes. The class is chosen from what an outage costs – and the same class should apply to cooling and cabling.

ClassDesignMeans
Class 1One path, no redundancyA fault or maintenance stops the supply
Class 2One path with redundant componentsTolerates a fault in e.g. one UPS module, not in the path
Class 3Multiple pathsOne path can be maintained while the other carries the load
Class 4Multiple paths, fault tolerantTolerates a fault – except during maintenance

Source: EN 50600-2-2 (power supply and distribution).

02

Cooling

How warm the air may be, how it is controlled, and how much heat a rack gives off.

Temperature and air

18–27 °C at the server front

ASHRAE recommends 18–27 °C in the air the IT equipment draws in. It is the temperature at the front of the server that counts – not the room average. Ordinary servers (class A1) tolerate 15–32 °C, but those are limits, not operating points.

Racks stand front to front in a cold aisle and back to back in a hot aisle. When the cold aisle is closed with roof and doors (containment), the air does not mix, and the cooling can run at a higher temperature with less energy.

Source: ASHRAE TC 9.9, Thermal Guidelines for Data Processing Environments, 5th edition (2021).

Cold aisleHot air back to cooling18–27 °C

Density

Every kW in the rack is a kW of heat

Almost all the power a rack uses becomes heat that the cooling must remove. That is why UPS, distribution and cooling are sized from the same power per rack.

Uptime Institute’s 2025 survey shows an average of 7.6 kW per rack. More racks are now at 10–30 kW, while racks above 50 kW are still rare – but AI equipment is pushing up.

01020304050kW per rackAverage7.6 kWGrowing share10–30 kWRare> 50 kW
Source: Uptime Institute Global Data Center Survey 2025.
03

Efficiency

How much energy goes to things other than IT – and what must be reported.

PUE

What does the IT power cost in total?

PUE shows how much energy the data centre uses in total for every kWh that reaches the IT equipment. The rest goes to cooling, losses in UPS and distribution, lighting and other. Uptime Institute has measured a weighted average just above 1.5 – almost unchanged for six years. Choose the consumption and see the PUE.

Cooling relative to the IT load

Losses in UPS and distribution

PUE 1.48incl. 3 % for lighting and other

IT 100Cooling 4053
Energy, IT = 100
PUE = total data centre energy ÷ IT equipment energy (ISO/IEC 30134-2). 1.0 is the theoretical minimum.

Reporting

Above 500 kW the figures must be disclosed

Data centres with an installed IT power demand of at least 500 kW must report energy data and KPIs for the previous year to the EU database on data centres by 15 May each year. The requirement comes from Article 12 of the Energy Efficiency Directive and Delegated Regulation (EU) 2024/1364.

In Denmark the requirement is implemented by Executive Order no. 926 of 9 July 2024, and the Danish Energy Agency supervises. It requires that energy to IT can be metered separately from the rest of the data centre.

  1. 1MeteringEnergy to IT and to the whole data centre
  2. 2KPIsE.g. PUE, water use (WUE) and energy reuse (ERF)
  3. 3ReportingTo the EU database by 15 May
  4. 4SupervisionThe Danish Energy Agency can issue orders
04

Norwerk

What we supply and service for data centres.

UPS system in a data centre

Norwerk

The power supply for your data centre

Norwerk designs, supplies and services standby power for data centres – from a single UPS to the whole chain with generator and STS. We load test the systems before they go into operation.

AreaWhat
UPS systemsBorri single- and three-phase UPS, also modular
Rotary UPSDRUPS and flywheels from Piller and HITEC
STSBorri STS 300 for single-corded equipment
Generator plantsDiesel generators for long autonomy
UPS batteriesSupply, testing and replacement
Fuel cellsHydrogen as standby power for smaller sites

FAQ

Questions and answers about data centres

Can’t find the answer? Give us a call.

+45 50 53 13 17
What are the availability classes in EN 50600?

EN 50600 divides the data centre’s power supply and distribution into classes 1 to 4. Class 1 is a single path without redundancy, class 2 a single path with redundant components, class 3 multiple paths so one can be maintained during operation, and class 4 multiple paths that tolerate a fault.

What is A/B supply?

Each rack is supplied from two independent paths, A and B, typically from separate UPS systems. Servers with two power supplies connect to both paths and keep running if one fails. Equipment with one power supply needs a static transfer switch.

How warm may a data centre be?

ASHRAE recommends 18–27 °C in the air drawn into the IT equipment. It is the inlet temperature at the front of the server that counts – not the room average.

What is PUE?

Power Usage Effectiveness is the data centre’s total energy consumption divided by the IT equipment’s energy consumption, defined in ISO/IEC 30134-2. A PUE of 1.5 means that for every kWh to IT, 0.5 kWh is used for cooling, losses and other.

Which data centres must report energy data?

Data centres with an installed IT power demand of at least 500 kW must report energy data and KPIs to the EU database by 15 May each year. In Denmark this follows from Executive Order no. 926 of 9 July 2024, supervised by the Danish Energy Agency.

How much power does a rack use?

Uptime Institute’s 2025 survey shows an average of 7.6 kW per rack. More racks are now at 10–30 kW, while racks above 50 kW are still rare.

What does Norwerk supply to data centres?

Norwerk designs, supplies and services the power supply: Borri UPS systems, rotary UPS, static transfer switches, generator plants, fuel cells and UPS batteries – plus load testing of the systems.

Do you have a project or a system that needs service?

Send us the load, required autonomy and voltage level – or describe the task. We will come back with a solution sized for your operation.

+45 50 53 13 17kontakt@norwerk.dkGet a quote